Africa’s AI data centre boom is mostly on paper.

Africa has announced far more AI compute than it runs. The continent operates roughly 400 to 500 MW of data-centre capacity, more than 60% of it in South Africa. Announced AI-focused campuses in Morocco, Egypt, Nigeria and Kenya alone add more than that again, and most have no build date. The gap has a price: Nigerian organisations alone spend about US$850 million a year on foreign cloud services, by Kasi's estimate.

Article

Africa’s AI data centre boom is mostly on paper.

Africa has announced far more AI compute than it runs. The continent operates roughly 400 to 500 MW of data-centre capacity, more than 60% of it in South Africa. Announced AI-focused campuses in Morocco, Egypt, Nigeria and Kenya alone add more than that again, and most have no build date. The gap has a price: Nigerian organisations alone spend about US$850 million a year on foreign cloud services, by Kasi's estimate.

19 November 202612 min read

AI series · Part 2 of 11

Africa has announced far more AI compute than it runs. The continent operates roughly 400 to 500 MW of data-centre capacity, more than 60% of it in South Africa. Announced AI-focused campuses in Morocco, Egypt, Nigeria and Kenya alone add more than that again, and most have no build date. The gap has a price: Nigerian organisations alone spend about US$850 million a year on foreign cloud services, by Kasi’s estimate.

Governments are already negotiating deals on the strength of these announcements. A 500 MW AI factory with no power contract or build date is still only a plan, and its backers may never build it. Our first piece asked who owns Africa’s AI; to answer that, we first need to know what has actually been built.

Only a handful of sites in Africa run dedicated AI chips today, most of them in South Africa and Lagos. The rest of the pipeline is waiting on power, chips and customers willing to pay.

Outside the industry, this shows up in three places: what people pay for electricity and how often it cuts out, where their bank and health records are stored, and whether the AI tools they use work in their own languages. Each depends on what gets built, where, and who owns it.

~450 MWof data-centre capacity running across Africa
60%+of it in South Africa
US$850ma year Nigerian organisations spend on foreign cloud
~1/3of built capacity in use, outside South Africa

What is running today is small, and mostly in South Africa and Lagos

Estimates of Africa’s operating capacity range from about 409 MW to “over 500 MW”, depending on who counts and whether they mean IT load or total power. Either way it is less than a single large US AI campus, and it is lopsided by region. Southern Africa holds more than 60%, almost all of it in South Africa, where Teraco alone runs close to 190 MW of IT load. West Africa comes a distant second, concentrated in Lagos, with Ghana’s Agility campus (30 MW committed) the next-largest site. East Africa’s capacity sits mostly in Nairobi and Mombasa, and North Africa’s two contenders, Egypt and Morocco, publish little at all.

Counts differ by source. Nigeria’s live capacity is 28 MW on Xalam Analytics’ estimate and 50 to 56 MW on TechCabal’s tally of commercial sites, with about 124 MW built once unequipped halls are counted. Kenya, East Africa’s hub, runs between 13 and 20 MW depending on the count. Egypt’s Cairo market runs about 14 MW on Knight Frank’s count, and Morocco publishes no national total. Ethiopia runs about 10 MW, mostly through Raxio and Wingu in Addis Ababa’s ICT park. It also has what most of the continent lacks: surplus hydropower, some of it already sold to bitcoin miners, and a cool highland climate. With an AI-ready operator, it could move up this map quickly.

Exhibit 1

South Africa runs most of Africa’s live capacity

Live IT load, MW. South Africa about 350; the next seven markets about 74 combined.

South Africa
~350
Nigeria
28
Egypt (Cairo)
14
Kenya
13
Ethiopia
~10
Ghana
4.8
Côte d’Ivoire
3
Rwanda
under 1

Sources: Xalam Analytics country briefs (2024–25 estimates); Knight Frank Data Centre Atlas 2026 (Cairo); Raxio (Côte d’Ivoire). Morocco publishes no live figure. Analysis: Regenerative Africa.

Is 50 MW a lot? For building AI, no. It is a fortieth of the 2,000 MW Colossus campus in Tennessee and about 5% of the grid power Lagos receives. Filled with AI servers, it would hold roughly 35,000 H100-class GPUs, about twice the 16,000 Meta used to train Llama 3.1, one of the largest open models.

For using AI, it goes further than it sounds. Google says a typical Gemini text prompt uses about 0.24 Wh, counting cooling and idle machines. At that rate 50 MW could answer around 5 billion prompts a day, more than 20 for every person in Nigeria, though less efficient hardware would cut that sharply. In practice Nigeria’s capacity runs none of this: it hosts bank, telecom and cloud workloads, plus a few racks of GPUs.

Dedicated AI compute is a thin layer on top. Cassava’s first AI factory, in Cape Town, came online around June 2026, the first phase of 3,000 GPUs it plans for South Africa. Kasi Cloud opened the first phase of its Lagos campus in May 2026 with Nvidia H100 and H200 GPUs, in undisclosed numbers. Stratos Lab began installing 400 Nvidia B300s at a Centurion data centre in August. Nigeria’s government AI hub in Abuja runs on one server of eight H200s.

Exhibit · The compute map

South Africa runs more than the next eight countries combined

Data-centre capacity running, being built and announced, AI chips in service and main owners, by country
CountryRunning today (live IT)Being builtAnnouncedAI chips runningMain owners
South AfricaAbout 350 MWAbout 60 MWAbout 260 MW firm; expansions toward 1,200 MW+Cassava, Cape Town (first phase of 3,000 GPUs); Stratos Lab, 400 B300s installingDigital Realty (Teraco), Africa Data Centres (Cassava), Vantage, Microsoft
Nigeria28 MW45 MWAbout 25 MW firm; Kasi to 100 MW; MTN 150 MW with South AfricaKasi (H100 and H200, count undisclosed); government hub, 8 H200sRack Centre, Equinix (MDXi), Kasi, Airtel Nxtra, OADC
Egypt14 MW (Cairo)Not published53 MW in Cairo; Cassava, Vodafone and Elsewedy 200 MWCassava and Vodafone GPU service launchingKhazna (G42), Vodafone, Elsewedy
Kenya13 MW30 MWAbout 50 MW firm; iXAfrica 18 MW and 53 MW sitesNone at scaleDigital Realty (iColo), iXAfrica, Africa Data Centres, Safaricom
EthiopiaAbout 10 MWNot publishedNot publishedNone documentedRaxio, Wingu, RedFox
Ghana4.8 MW7 MWAgility campus, 30 MW committedNone documentedEquinix, Digital Realty, PAIX, Africa Data Centres, MTN
Côte d’Ivoire3 MW at Raxio, the main neutral siteNot publishedNot publishedNone documentedRaxio
RwandaUnder 1 MWAfrica Data Centres, KigaliPAIX site plannedNone documentedAfrica Data Centres, PAIX
MoroccoNot publishedNot publishedNexus and Naver 500 MW; Iozera 386 MW; Dakhla 500 MWNone documentedNexus consortium (Naver, Nvidia, Lloyds Capital), Iozera
Dedicated AI chips in service or installing. Live, under-construction and firm pipeline figures are Xalam Analytics estimates for 2024 and 2025, except Egypt (Knight Frank, Cairo market) and Côte d’Ivoire (Raxio). AI chips and named projects from company announcements and trade press. Analysis: Regenerative Africa.

Live, under-construction and firm pipeline figures are Xalam Analytics estimates for 2024 and 2025, except Egypt (Knight Frank, Cairo market) and Côte d’Ivoire (Raxio). AI chips and named projects come from company announcements and trade press, listed in Sources.

Most of the pipeline is a press release, not a project

Most of the big AI campuses are missing at least one basic: a site, a power contract, financing or a start date. Morocco’s 500 MW Nexus AI factory near Casablanca has a US$1.2 billion budget, named partners and a renewable supplier, but no construction start or completion date. Dakhla’s 500 MW has less. Egypt’s US$1 billion Cassava, Vodafone and Elsewedy facility commits only its first 20 MW, over three years.

Exhibit 2

Morocco has announced about 1,400 MW and runs none on record

Capacity running today against capacity being built or announced, MW

Running todayBeing built or announced
Morocco
none on record
1,386
South Africa
350
320
Egypt
14
200
Kenya
13
80
Nigeria
28
70

Being built or announced: Xalam Analytics firm pipeline for South Africa, Kenya and Nigeria; largest named projects for Morocco (Nexus and Naver 500 MW, Iozera 386 MW, Dakhla 500 MW) and Egypt (Cassava, Vodafone and Elsewedy, 200 MW). Analysis: Regenerative Africa.

The projects with dates are late or shrinking. Kenya’s Olkaria campus, which we covered in the first article in this series, is still on hold. Airtel’s 38 MW Nxtra facility in Lagos missed its early-2026 target. Cassava bought 12,000 Nvidia GPUs, but has only placed the first South African phase; Kenya, Nigeria, Morocco and Egypt are “being lined up”.

Even built capacity is underused. Across Africa, about one-third of built data-centre capacity is in use, according to the Africa Data Centres Association. Operators build halls ahead of demand and fill them slowly. The big cloud providers still serve most of Africa from Europe or Cape Town (Nigeria has no full cloud region), and data-localisation rules are only now pushing workloads home. Local buyers are small too: Nigerian operators report that banks and telecoms looking for GPUs want three or four racks at most. Building ahead of demand is normal in this industry; building ahead of power is not.

Four types of owners are building, each wanting something different

Exhibit 3

Four types of owners are building, each wanting something different

Owner
Who
They want
Kept locally
Global colocation
Digital Realty, Equinix
Rent from anyone who pays
Little
Telecoms
Cassava, Airtel, MTN, Vodafone
GPU time for customers they already have
Some
Foreign and Gulf capital
Khazna (G42), Naver, Nexus
Large campuses, often for export
Least, despite biggest sums
African-led
Kasi, iXAfrica
Local customers and sovereign cloud
Most

Analysis: Regenerative Africa, from company announcements and trade press.

Much of the capacity running today belongs to global colocation firms: Digital Realty owns Teraco in South Africa and iColo in Kenya, and Equinix owns MDXi in Nigeria. They rent space and power to anyone who pays, hyperscalers included, and the profits go to shareholders abroad.

Telecom groups are moving into AI compute because they already have sites, fibre and enterprise customers. Cassava, Airtel’s Nxtra, MTN and Vodafone Egypt are all building or partnering. Their interest is selling GPU time to the customers they already serve, which makes them the most likely route to local AI use at scale.

Foreign strategic and Gulf capital funds the biggest announcements. Abu Dhabi’s Khazna, part of G42, announced a US$250 million, 25 MW data centre in Cairo with local partner Benya Group in 2023. MTN’s 150 MW AI venture is with Tarek Al Ashram. Morocco’s Nexus consortium includes Korea’s Naver Cloud and Lloyds Capital alongside Nvidia. These projects bring the largest sums and the least local ownership.

African-led operators are the smallest group but the closest to sovereign by design. Kasi in Lagos, with Nigeria’s sovereign fund as an investor, is the clearest case; Nairobi-based iXAfrica, which hosts Kenya’s sovereign public cloud, is another. Lagos operators have already beaten the two usual objections, unreliable power and no local demand: Kasi runs Nvidia H100 and H200 GPUs for Nigerian customers today, and Rack Centre, Nigeria’s largest operator by live capacity, runs on its own gas plant and has never connected to the grid. Their constraint is capital: a Tier III megawatt costs about US$10 million to build.

Power, not buildings, decides which of these get built

The map is really a power map. Kenya’s grid peaked at about 2,440 MW in January 2026 against 2,495 MW of firm capacity, a reserve margin of about 55 MW. A single 100 MW AI campus would need almost twice that. Nigeria’s grid delivers 4,000 to 5,000 MW, so serious operators generate their own: Rack Centre has never connected to the grid, and diesel power costs US$0.28 to US$0.33 per kWh. South Africa’s announced expansions would add load roughly equal to one stage of load-shedding, and Eskom’s own outlook warns of constrained supply by 2029.

Exhibit 4
Today

Kenya’s grid had about 55 MW to spare in January. One 100 MW AI campus needs almost twice that.

Gas would cost Kenya about US$155m a year more than geothermal

Cost of power in Kenya’s long-term plan, US cents per kWh; the gap is for a 100 MW facility at full load

Gas
27.7¢
Geothermal
10¢

Sources: Kenya Least Cost Power Development Plan 2024–2043, via Tech-ish (Nov 2026); January 2026 peak demand via Lineserve. Gap = 100 MW × 8,760 hours × 17.7¢, Regenerative Africa calculation.

For governments, this changes the negotiation. A project that cannot show where its power comes from is not yet an investment, and incentives should follow commissioned megawatts, not announced ones. The strongest hand belongs to the country that can offer firm, clean power, as Kenya can at Olkaria and Morocco claims it can with TAQA, and it should be priced as such. Before signing, a government should see four things in writing: where the power comes from, who owns the facility, how much capacity is reserved for local users, and who carries the cost if the project stalls.

Exhibit 5

Before signing a data-centre deal, see these four in writing

What a government should require of any AI or data-centre project

?
Where the power comes fromA signed power contract, not a promise, and what it does to the grid
?
Who owns the facilityThe equity split, and whether a local partner holds part of it
?
Capacity reserved for local usersHow much compute local banks, start-ups and government can buy
?
Who pays if it stallsGuarantees, penalties and what the state is exposed to

Kenya is already testing that hand. In November, Greek firm AMACO Energy and ARISE IIP signed a memorandum for a floating gas power barge near Mombasa, worth about US$700 million, to power AI data centres and an industrial park. It would start at 250 MW and could grow to 1,000 MW. So far only a memorandum has been signed, and no data-centre customer has been named. Gas would also cut against Kenya’s own record: about 90% of its grid power is renewable, and its long-term power plan ranks gas last of nine baseload options on cost, at about 27.7 US cents per kWh against 10 cents for geothermal. Run at full load, 100 MW of gas at that price would cost about US$155 million a year more than the same power from geothermal.

For investors, the opportunity is not the largest announcement but the bottleneck. Local GPU-as-a-service, where banks and other regulated firms rent AI chips by the hour, inside their own country, from providers such as Cassava, Kasi or Stratos Lab, is a real and growing market: Nigeria’s central bank requires banks, fintechs and payment firms to keep transaction data in the country from January 2027. Power generation tied to data-centre offtake and mid-sized, phased halls look more bankable than gigawatt campuses.

What this map leaves open

The map raises questions we take up later in this series. Who pays for the build matters as much as who owns it: Gulf, Korean and US money each come with their own terms, and US export controls now decide who can buy the best chips. Our sixth piece follows that money. Power is the other open question. Kenya’s gas barge shows how quickly an AI promise can pull a clean grid towards fuel, and our fifth piece looks at how to price power and water into a data-centre deal.

Two deeper questions sit underneath. Do countries whose AI capacity is African-led, such as Nigeria and Kenya, write different AI strategies from those that import theirs? We return to that in our piece on national AI strategies. And should every country want a data centre at all? We will make the full case against. The next piece in the series asks who owns Africa’s training data.

Sources

Accessed 17 November 2026. Capacity figures are as reported by each source; estimates differ by method, and few operators publish GPU counts.

  1. Nairametrics, Africa’s data centre capacity exceeds 500 MW with 890 MW in pipeline (Fortren & Company report, Jul 2026)
  2. Daily Maverick, Major SA data centre expansion plans emerge (Feb 2026)
  3. TechCabal, CBN’s local data order puts Nigeria’s data centres to the test (Jul 2026)
  4. The AI Innovator, Nigeria is building for the AI boom; customers are slower to arrive
  5. Technext, A comprehensive list of the 28 data centres in Nigeria (Jun 2026)
  6. Lineserve, Data centres in Kenya: the complete verified list (Sep 2026)
  7. iAfrica, Nvidia confirms Morocco in two African AI compute projects (Sep 2026)
  8. Global Flow Control, Morocco advances US$1.2bn AI data centre project (Apr 2026)
  9. Hespress, Egypt moves to build US$1bn AI data centre with Nvidia tech (Sep 2026)
  10. Billionaires.Africa, Cassava plans 20 MW Joburg AI factory as Cape Town goes live (May 2026)
  11. Billionaires.Africa, Cassava builds out 12,000-GPU Nvidia AI network (Nov 2026)
  12. TechCentral, Nvidia’s top AI chips are coming to a Centurion data centre (Aug 2026)
  13. AI Chat Daily, Nvidia stakes Egypt and Africa AI push (Sep 2026)
  14. Google Cloud, Measuring the environmental impact of AI inference (Aug 2025)
  15. Meta, Introducing Llama 3.1 (Jul 2024)
  16. CairoScene, UAE-based Khazna will establish US$250 million data centre in Egypt (May 2023)
  17. Tech-ish, A Greek company wants to build a floating gas power plant in Mombasa for AI data centres (Nov 2026)
  18. Green Building Africa, Kenya signs US$692 million LNG power deal for Mombasa industrial park and AI data centres (Nov 2026)
  19. Xalam Analytics, South Africa data center market briefing (Jul 2025)
  20. Xalam Analytics, Nigeria data center market briefing (Jan 2026)
  21. Xalam Analytics, Kenya data center market briefing (Jul 2025)
  22. Xalam Analytics, Ghana data center market briefing (Jul 2025)
  23. Xalam Analytics, East Africa data center markets brief (May 2025)
  24. Knight Frank, Data Centre Atlas 2026
  25. Africa Data Centres Association, Data Centres in Africa 2026
  26. Connecting Africa, Raxio opens data center in Côte d’Ivoire (Sep 2024)
  27. Addis Fortune, Raxio doubles Ethiopia capacity (Sep 2023)
  28. AllAfrica (Daba Finance), Morocco attracts data center investments despite power, demand gaps (Jan 2026)
  29. Addis Fortune, bitcoin mining’s power use in Ethiopia
  30. Regenerative Africa, Africa’s AI strategy doesn’t have to be borrowed (Nov 2026)

Ready to work with us?

Let's build something
that lasts.

Book a consultation
Stay Informed

Get Notified

Be the first to know when new events are announced.

You're on the list.

We'll reach out as soon as the event is confirmed.

1
Details
2
Cart
3
Payment
Your Details
Your Cart
—
—
$0.00
Subtotal$0.00
Registration fee$0.00
Total$0.00Free
Confirm & Pay
—— · —
Order Summary
—$0.00
—
Total Due Today$0.00
No payment required — this is a free event. Your spot will be confirmed immediately.

Registration Confirmed

A confirmation is on its way to your inbox.
We look forward to seeing you.

Cookie choice